Some of Our Projects

01

5 TPH@10 bar(g) STEAM BOILER PLANT

Tekkawatta, Biyagama, Sri Lanka

Client

Coca Cola Beverages Sri Lanka Ltd

Installation of 5 TPH/10 bar(g) bio-mass steam Boiler plant at Coca Cola Beverages Sri Lanka Ltd at Biyagama. Steam Boiler supplier – Veesons energy Systems pvt ltd, India.

Dates Employed

Nov 2012 – Jan 2013

Employment Duration

3 Months
02

5 TPH@21 bar(g) STEAM SYSTEM PACKAGE

Bokundara, Piliyandala, Sri Lanka

Client

Gislaved Gummi Lanka (pvt) Ltd

Installation of 5 TPH/21 bar(g) bio-mass steam Boiler plant at Gislaved Gummi Lanka (pvt) Ltd (Elastomeric) at Bokundara. Steam Boiler supplier – Industrial Boilers ltd, India.

Dates Employed

Mar 2013 – Sep 2013

Employment Duration

7 Months
03

1 MnkCal/hr HWG SYSTEM

Galaboda

Client

Finlays Tea factory, Hapugasthenna Plantation

Installation of 1 MnkCal/hr bio-mass fired Hot Water Generator plant at Hapugasthenna Plantation, Galaboda, Rathnapura . HWG supplier – Thermotech Systems ltd, India.

Dates Employed

Aug 2013 – Feb 2014

Employment Duration

7 Months
04

5 TPH@10 bar(g) STEAM SYSTEM PACKAGE

Ranala

Client

Ceylon Cold Stores

Installation of 5 TPH/10 bar(g) bio-mass steam Boiler plant at Ceylon Cold Stores,Ranala . Steam Boiler supplier – Industrial Boilers ltd, India.

Dates Employed

Aug 2013 – Feb 2014

Employment Duration

7 Months
05

1 MnkCal/hr TFH SYSTEM

Sirikanthi Enterprises, Panaluwa Industrial Estate, Panaluwa

Client

Sirikanthi Enterprises

Installation of 1 MnkCal/hr bio-mass fired Hot Water Generator plant at Sirikanthi Enterprises, Panaluwa Industrial Estate, Panaluwa.

Dates Employed

Aug 2013 – Mar 2014

Employment Duration

8 Months
06

11 MnkCal/hr (12.5 MW)@18 kg/cm2 :biomass HWG system

BEPZ, Biyagama

Client

Ansell Lanka Pvt Ltd

Installation of Eleven (11) MnkCal/hr (12.5 MW) -18 kg/cm2 pressure bio-mass fired Hot Water Generator plant at Ansell Lanka (pvt) Ltd, Biyagama

Dates Employed

Nov 2013 – Oct 2014

Employment Duration

1 Year
07

4 TPH/12 bar(g) STEAM BOILER SYSTEM PACKAGE

Horana

Client

Elastomeric Engineering Company Ltd

Installation of 4 TPH/12 bar(g) bio-mass steam Boiler plant at Elastomeric Engineering Company Ltd at Horana. Steam Boiler supplier – Industrial Boilers ltd, India.

Dates Employed

Oct 2014 – Dec 2014

Employment Duration

3 Months
08

2 MnkCal /hr TFH SYSTEM

BEPZ, Biyagama

Client

Noyon Lanka pvt Ltd

Dates Employed

Feb 2015 – Jun 2015

Employment Duration

5 months
09

6 MnkCal /hr TFH SYSTEM

Pugoda

Client
South Asia Textile Industries Lanka pvt ltd

Dates Employed

Jun 2015 – Apr 2016

Employment Duration

11 months
10

0.8 MnkCal/hr HWG SYSTEM

Ella, Bandarawela

Client
Newburgh Green Teas, (Finlays)

Installation of 0.8 MnkCal/hr bio-mass fired Hot Water Generator plant at Newburgh Green Teas, (Finlays), Ella. HWG supplier – Thermotech Systems ltd, India.

Dates Employed

Jun 2015 – Sep 2015

Employment Duration

4 months
1 2